Manunda Place Building Construction



Click the photo for more pictures
Project Title: Construction of a Nine Storey Building in the Darwin CBD
Project Scope: To manufacture, deliver and install iH2O HVAC Piping across all 9 Floors plus the Central Plantroom of the building
Primary Contractor: Hutchinson Builders
Client Name: VAE Group/ Select Services NT
Location: The corner of Cavenagh & Knuckey Streets Darwin City
APS Contract Value: $800,000
Description of the Job (problems we solved): APS worked closely with VAE’s Team in the installation of and commissioning of the HVAC piping infrastructure across the whole of the Manunda Place Building. APS installed the condenser water pipework across all 9 floors of the building. Our Team piped-up the PAC units and ran condenser water drains from each of the PAC units. APS installed the chilled and condenser water pipework in the 9th Floor Chiller Plantroom. We assisted the client to pipe the condenser water from the cooling towers which included a side-stream filtration system. The APS Site Project Team fitted all the high level chilled water, securing it with seismic bracing. Our team eliminated the need for seismic support systems for all lower level pipework by designing and installing bespoke pipe stands which are rated to the same.